Successful start-up in Linz-Unkel
The belt-dryer of ELIQUO STULZ produces optimal results – only few days after start of the commissioning. The sludge is dried to more than 90 %. Consequently the PYREG®-plant could be started in the same week.
The schedule for the erection was strictly adhered to. The commissioning started exactly on June 26th. 2015 – according to plan.